The fibonacci facade has by now progressed 5 floors since 6/9/2010. At this rate, completion of all facade works can be anticipated by end of December 2010. With fibonacci 3 segments being installed, the geometrical progression has become more apparent in the facade. WCT and Avos had done a commendable job in fabricating the facade, and we hope to see fibonacci 2 segment at levels 36 and 37, the highest two office floors, to be completed by next month, leaving the skylight structure of fibonacci 1+1 at the mechanical levels to be installed come December 2010.