4G9 Tower: Progress as at 6/9/2010




The Fibonacci curtain wall facades have progressed 5 floors since 10/8/2010 (Fibonacci 8 completed and 3 floors of Fibonacci 5 facade). With only 7 floors to go (2 floors remainder of Fibonacci 5, 3 floors Fibonacci 3 and 2 floors Fibonacci 2), and if WCT maintains the current rate of progress the facade may be completed by the 3rd week of October 2010. In November and December they could work on the skylight (Fibonacci 1 + 1 of the equation) and the roof covering for the maintennance gondola.